Public Consultation · Now Open

Brighouse Power

Proposed Battery Energy Storage Facility on land south of Armytage Road, Brighouse, HD6 1PT.

Consultation Opens

01 Aug 2026

Consultation closes

30 Sept 2026

Planning Authority

Calderdale Council

submission

Autumn 2026 (Anticipated)

About the Project

What is Brighouse Power?

Brighouse Power is a proposed Battery Energy Storage System (BESS). The batteries would charge when electricity demand is lower, or when surplus electricity is available, and release it back to the network when demand is higher - helping balance supply and demand and enabling more renewable electricity to be used.

The facility would not generate electricity itself. It would store electricity already available on the network and release it when required.

Key elements of the proposal

✓ 18 battery storage units and associated transformers/inverters

✓ Internal access road, parking and turning areas

✓ Perimeter security fencing, controlled gates and CCTV

✓ Acoustic fencing and raised equipment platforms

✓ Surface-water drainage, landscaping and biodiversity enhancement

40MW

/ 80MWh capacity

18

Battery units

40 yrs

Operational life

14 mo

Construction (from 2028)

Site Selection

Why has this location been selected?

The site has been identified because of its proximity to the existing electricity network and Brighouse substation, reducing the length of underground cabling required and limiting unnecessary construction disturbance.

The site selection and design process has also considered:

✓  Access to the electricity network 

✓  Relationship with nearby residential and commercial properties

✓  Construction access, flood risk and drainage

✓  Landscape, visual effects, ecology and biodiversity

✓  Noise, historic environment and land quality

✓  Mineral safeguarding, fire and operational safety

Have Your Say

We'd like to hear your views

The questionnaire asks about your overall view of the proposal, the issues that matter most to you, topics you’d like more information on, potential local benefits, and any changes you’d like the project team to consider.

Consultation deadline: 30 September 2026 (TBC)